Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Grand Strand renourishment project resumes in Myrtle Beach, set to be completed by end of summer

Construction activities continue during the Grand Strand Renourishment project in North Myrtle Beach, South Carolina, Jan. 22, 2026, during a site visit by the U.S. Army Corps of Engineers, Charleston District. In December 2024, the Charleston District awarded a contract to Great Lakes Dredge and Dock Company to place approximately two million cubic yards of sand—equivalent to 200,000 dump trucks—along 26 miles of Myrtle Beach. Construction began on the northern end of North Myrtle Beach in December 20
Dylan Burnell
/
U.S. Army Corps of Engineers
Construction activities continue during the Grand Strand Renourishment project in North Myrtle Beach, South Carolina, Jan. 22, 2026, during a site visit by the U.S. Army Corps of Engineers, Charleston District. In December 2024, the Charleston District awarded a contract to Great Lakes Dredge and Dock Company to place approximately two million cubic yards of sand—equivalent to 200,000 dump trucks—along 26 miles of Myrtle Beach. Construction began on the northern end of North Myrtle Beach in December 20

A project aimed at protecting beachfront infrastructure along the Grand Strand is scheduled to be completed by August.

The U.S. Army Corps of Engineers says the Grand Strand Renourishment project in Myrtle Beach is back underway. Work resumed on May 29 and is anticipated to wrap up by early July. Then, crews will transition to the Surfside beach area.

Sand placement is expected to finish by the end of August, but engineers say factors such as weather, mechanical issues, or other unforeseen delays can affect the construction schedule and impact the timeline.

Beachgoers are reminded to be aware of construction zones and posted signage.

Crews say the purpose of this project is to increase coastal storm management and protect infrastructure. In its update, the Corps of Engineers said, "by building a wider, higher beach and dune system, we can absorb the energy of powerful storm waves."

Real-time progress can be tracked online. The renourishment is funded entirely by the Corps of Engineers and is said to cost $72 million.

Kristina Thacker joined the South Carolina Public Radio team in September of 2025. She is a multimedia journalist with experience in both on-air reporting and production.